Real-World
Experiences with Fusion-Crete®
|
|
Ramping
of Bridge Deck to Compensate for Settling
|
|
|
|
(click
on thumbnails for enlarged photos)
|
 |
The
surface of this bridge deck has settled as much as 3 inches in
two directions beginning at the crown. |
 |
After
some grinding and pressure washing, the areas to be "ramped" are
being primed with FUSION-CRETE® "premix". A stronger
bond may be achieved with use of a slurry coat. |
 |
A
very dry mix of FUSION-CRETE®
"premix",
Portland cement and silica sand (#30-mesh), prepared in wheelbarrows,
has been applied to the bridge surface where needed and is being compacted,
trowel-finished and feathered out to absolute zero. |
 |
Some
of the crew members can be seen continuing this process just beyond
the bridge's crown where the settling has occurred in the opposite
direction. |
 |
This
photo, taken the following day, shows the FUSION-CRETE®-fortified
ramping material set up and feathered out to zero in two directions.
This ramping material is flexible, fully load-bearing and extremely
weather-resistant. This material will have set up sufficiently in
24 hours to open this lane for vehicular traffic. |
|
Estimated total time required: 8 hours
|
| BACK